About this report

The Program Increment Analysis report provides a breakdown of financial data for selected PIs within a portfolio. Financial data such as CapEX, OpEX, Labor, Budget, and Spend are rolled up and displayed for the target PIs, and totals are given for the associated portfolio. The report displays in the form of a data table, and is aimed at the PMO and executives of your company.

Navigation

  1. Select the Reports icon from the left Navigation menu.
  2. Start typing the report's name in the Search box. 
  3. Once found, select the report.

Note: You can also use the categories on the left to search for the needed reports.

Prerequisites

  1. Portfolio must exist in the system
  2. Program most exist in the system and be tied to the portfolio
  3. PI must exist in the system and be tied to a program
  4. Sprints must be created and tied to the PI
  5. Epics must be created and assigned to a program and PI; enter CapEx and OpEX values for epics
  6. Teams must be created and assigned to sprints; cost per team member must be defined by cost centers
  7. Features must be created and assigned to epics
  8. Stories must be created and assigned to features; LOV and LOE values must be entered for stories

How are report values calculated? 

Start: the start date of the PI, pulled from the PI grid/Details panel

Finish: the finish date of the PI, pulled from the PI grid/Details panel

CapEx: sum of epic capital expenditures budgeted for the project, as entered on an epic's Finance tab

OpEx: sum of epic operational expenditures budgeted for the project, as entered on an epic's Finance tab

Labor: sum of costs for each team member assigned to sprints in the PI; cost per person defined via cost centers

Budget: budget for the PI, entered on the PI's General tab

Spend: sum of CapEX + OpEX + Labor

Value: sum of LOV points for stories assigned to the PI

EI: effort index = LOV points / LOE points

B/S: budget to spend index = sum of CapEX + OpEX + Labor / budget 

PICompare.png

How to interpret this report

Executives should use the data to review overall financial and value status of PIs within a portfolio.

Was this article helpful?
0 out of 0 found this helpful
Print Friendly Version of this pagePrint Get a PDF version of this webpagePDF

Join the Atlassian Community!

The Atlassian Community is a unique, highly collaborative space where customers and Atlassians come together. Ask questions and get answers, start discussions, and collaborate with thousands of other Jira Align customers. Visit the Jira Align Community Collection today.

Need to contact Jira Align Support? Please open a support request.