Generate sprints for all PI teams

Next, you need to generate sprints with the same dates for every team participating in the PI. The programs associated to the PI determine which teams participate in the PI.

Generate sprints for all teams in a PI on the program increments page:

  1. Select Programs in the top navigation bar and select the program containing the PI that you want to create sprints for.
  2. On the sidebar, select More items in the list of options.
  3. Select Program increments; the program increments page displays.

To generate sprints for all PI teams:

  1. On the program increments page, select the necessary PI from the grid.
  2. Open the Sync Sprints tab.
  3. In the Current Sprints section, click Generate Team Sprints.

To update anchor sprint dates and push those dates to all team sprints, select new Standard Sprint Dates for the desired anchors and then switch on the Update Sprints with Dates setting and click Save

Jira Align automated sprint naming

pastedImage.png

 

Was this article helpful?
1 out of 2 found this helpful
Print Friendly Version of this pagePrint Get a PDF version of this webpagePDF

Join the Atlassian Community!

The Atlassian Community is a unique, highly collaborative space where customers and Atlassians come together. Ask questions and get answers, start discussions, and collaborate with thousands of other Jira Align customers. Visit the Jira Align Community Collection today.

Need to contact Jira Align Support? Please open a support request.